8 December 2022
November marked a major milestone for McGowan Environmental Engineering delivering the largest project they have undertaken to date, at Moy Wind Farm, south of Inverness
In mid-November the Aviemore based civil and environmental engineering contractor successfully completed the installation of over 60km of 33kV high voltage underground cable consisting of three circuits in trefoil for Scottish and Southern Electricity Networks (SSEN) Distribution at Moy. Utilising cable ploughing, open cut methods and Horizontal Directional Drilling, a huge multi-department team effort from McGowans over the last 12 months culminated with the circuits being connected to the national grid in recent days.
McGowans were awarded the Moy cabling contract by SSEN in October 2021 as part a £7.2m project to deliver a total of 81km of cabling across Inverness and Caithness. Due to increased windfarm yield from Moy Windfarm and the newly established Burn of Whilk windfarm in Caithness, the projects involved the installation of new 33kV single-circuit and triple-circuit underground cabling, fibre-optic cable, cross-bonding and intermediate earthing across rural and urban areas.
Speaking about wrapping up the vital £7.2m projects, Darren Hendry Managing Director of McGowan Environmental Engineering, said:
“We are all delighted at Mcgowan Environmental Engineering to have recently completed the combined Moy and Burn of Whilk cable installation projects. This marks a great milestone for our team within the industry as we look to grow organically within the energy sector through our innovative and people-focused approach.”
Donald L. MacKinnon, Head of Large Capital Delivery (SHEPD) at Scottish and Southern Electricity Networks, commented:
“Both Moy and Burn of Whilk projects ran very smoothly considering the distances, terrain and number of landowners involved – this is testament to the hard work and professionalism shown by both the project teams at McGowans and SSEN.”
Douglas Munro, Senior Project Manager at McGowan Environmental Engineering, said:
“The projects have been a huge success thanks to the combined effort of all parties involved: SSEN, landowners ,our supply chain, and the local communities who have been impacted by the works. We are appreciative of our highly skilled site delivery team at McGowans, delivering these projects safely and to the highest standard in some very challenging conditions."
McGowan Project Manager, Steven Mitchell, adds:
“Vital to the timely and cost-effective delivery of the project at Moy - with minimal impact on the sensitive landscape - was the deployment of McGowan’s proprietary new cable wrapping technology, Eco Cable Protect. The innovative cable protection, provided both projects with an efficient and effective installation solution, which is set to revolutionise the rural cabling sector.”
Eco Cable Protect allows for on-site preparation, production and installation, reducing project delivery times and costs whilst keeping any environmental impact in sensitive landscapes and habitats to a minimum.
McGowan Group Ltd
Unit 16, Dalfaber Industrial Estate,
Aviemore PH22 1ST
©2024 McGowan Group